*Road Work***repair on 3rd Street and Henry

Third Street Reconstruction from Vine St to Brown St will include full depth pavement remove and replace, curb and gutter remove and replace, and driveway approaches.  The roadway is to be repaved utilizing asphalt modified to include recycled rubber tires.  This pavement has been used on many streets throughout the city.

Construction will start September 17, 2018 and shall be finished October 13, 2018.  During construction, traffic will be detoured to Sixth St.

Murray Underground Systems is the Contractor for this project.

Henry Street from Fred Moore Highway to Clinton

Beginning this week, the contractor will begin preparations for the reconstruction of Henry Street from Fred Moore to Clinton. It is anticipated that this project will take 6 to 8 weeks to complete. Work will include the reconstruction of the road as well as the replacement of the catch basin leads and repairs to the sanitary sewer.

The contractor’s current schedule is as follows:

Mobilization and Tree Removal                                  October 3 – October 4

Pavement Removal                                                    October 5

Curb Removal                                                             October 8 – October 9

Install new Drainage and Sanitary Repairs                October 10 – October 12

Earth Excavation and Install New Aggregate Base October 15 – October 19

Concrete Curbs and Drive Approaches                      October 22 – October 26

Final Grading for New Asphalt                                    October 29 – October 31

Place first lift of New Asphalt                                      November 1 – November 2

Restoration                                                                 November 5 – November 9

Place final lift of New Asphalt                                     November 12 – November 15

After your driveway approach is removed, the contractor will place stone in your approach so that you can continue to use your driveway. When the new curb and gutter and your new driveway approach is poured you will not have access to your driveway and will have to find an alternate location to park. If you are handicapped, please contact Stephen Pangori (586) 726-1234 so that special arrangements can be made. There will be no interruption of emergency services at any time during construction.

Regular work hours during construction will be 7:00 a.m. to 5:00 p.m., Monday through Friday.

During construction, mail delivery and rubbish pick-up will not be interrupted.  On garbage collection day, the Contractor will pick up the garbage at your home at 7:00 A.M.  During construction, please have your garbage out to your sidewalk by this time. Please put your garbage out in bags only.  Recycling will be suspended within the construction area during the project.

If you are within the construction area and have a sprinkler system between the sidewalk and curb, please call Stephen Pangori at 586-726-1234 as-soon-as possible and please mark your sprinkler heads in this area before October 8th.  This will allow the contractor to remove the heads and lines from the construction area before work begins to avoid unnecessary damage to your system.  Your system will be reinstalled during restoration of the project.  We also ask that you turn off any zone on your system that is within 20 feet of the street.

The City of St. Clair wishes to apologize in advance of the impending construction for any inconvenience it may cause you and hopes, with your cooperation, to complete the construction in a timely manner.

If you have any questions or concerns, please feel free to contact any of the following:

Contractor: Murray Underground Systems, Inc. (810) 385-1967
Engineer: Anderson, Eckstein and Westrick, Inc
Stephen Pangori (586) 855-9551 – cell

(586) 726-1234 – office