M-29 Clinton to Bree: road work beginning Oct. 9
The Michigan Department of Transportation (MDOT) will close a section of M-29 at the railroad tracks south of the bridge and have single lane closures on M-29 from St. Clair Highway to Bree Road to complete concrete patches and replace the CSX Railroad crossing in the city of St. Clair.
This work is part of an overall $965,000 invest to improve 1.6 miles of M-29, including sidewalk ramp improvements compliant with the Americans with Disabilities Act (ADA).
Highway:
M-29
Start date:
Monday, Oct. 9, 2023
Estimated project end date:
Monday, Oct. 30, 2023
Traffic restrictions:
M-29 will be detoured via Bree Road, St. Clair Highway, King Road, and Fred Moore Highway.
Job numbers:
Based on economic modeling, this investment is expected to directly and indirectly support nearly 14 jobs.
Safety benefit:
This work will improve the driving surface of M-29 and the railroad crossing.